These are the dayshift crew from Vital Equity and TNB Remaco together with Mr Alex from Turbine Services who did the EGT Frame 9E gas turbine major inspection
in a local record time of 17 days(double shift)
breaking the previous known record set at the same site by a day.
Pok Ghani Long beside the turbine rotor.
Mahyiddin 'Chot' our experience crane driver
lowering the exhaust plenum roof.
Irwan watching over the loosening of the bearing no:1 cover bolts.
Ghani and Dollah 'hello' working on the bearing no:2 cover.
Faizul 'Panjang' and the turbine compartment side enclosure.